Every stand, from a shell-scheme upgrade to a double-decker, goes through the same seven stages. Knowing them helps you plan decisions and deadlines on your side.

1. Brief

Event, hall and stand number, dimensions and open sides, exhibitor manual, objectives, products or demos, meeting and storage needs, brand guidelines and budget range.

2. Concept and 3D design

Layout, visitor flow and branding presented as 3D visuals from several angles with a plan view. Revisions happen here, where changes are cheapest.

3. Technical drawings and approvals

Dimensioned drawings, structural information for tall or two-storey elements, and electrical layouts are submitted to the organiser before their deadline.

4. Fabrication

Joinery, metalwork, finishes, graphics and electrical work, followed by a test assembly before anything leaves for the venue.

5. Transport and installation

Delivery slots and contractor passes are booked; the crew builds within the official build-up period.

6. Handover and show support

Snag-free handover before opening, with a team on call during show days.

7. Dismantling and storage

Removal within the breakdown period; reusable elements are stored for your next show.

How long does it all take?

As a guide, shell-scheme upgrades need a few weeks, modular stands around a month, custom stands two to three months, and double-deckers longer. Organiser deadlines, not fabrication, are usually the constraint, so start at stage one as soon as your space is confirmed.

Questions clients ask

How long does exhibition stand fabrication take?

It depends on size and finish. As a planning guide, allow time for design and revisions, then organiser approval of the drawings, then workshop production, then the build-up days the venue allocates. Larger double-deck or heavily customised stands need more lead time than modular systems. The safest approach is to brief your contractor as soon as your space is confirmed; late briefs are possible but reduce design options and raise cost.

What should we prepare before asking for a quotation?

The event name and dates, your stand number with dimensions and open sides, the exhibitor manual if you have it, your objectives, the products or demos you will show, meeting and storage needs, brand guidelines and a budget range. With these, the first concept is usually close to final.

What happens to the stand after the show?

It is dismantled within the organiser’s breakdown period and removed from the venue. Reusable elements can be stored for your next event; the rest is recycled or disposed of responsibly.

Related articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Tell us about your next exhibition

Share the event, the stand size and your dates. We reply with questions if anything is unclear, then a costed proposal with 3D visuals.

PDF, image, Word or PowerPoint, up to 10 MB.

We reply within one working day. We use these details only to respond to your request. See our privacy policy.